ERP User Acceptance Testing: A Practical UAT Guide
How to run ERP user acceptance testing: test scenarios, end-to-end scripts, test data, who tests, logging issues, exit criteria and sign-off before go-live.
User acceptance testing (UAT) is the last chance to find problems before real orders, real stock and real money flow through the new ERP. It is also where users start to trust the system.
What UAT is for
UAT checks that the configured system supports the business processes as agreed. It is not a demo and not a training session. Testers try to break things.
Write end-to-end scenarios
Test full processes, not single screens:
- Order to cash: quote, order, pick, ship, invoice, payment
- Procure to pay: request, purchase, receipt, bill, payment
- Plan to produce: forecast, MRP, production, quality, finished stock
- Record to report: journals, reconciliation, month-end, reports
Include exceptions: partial deliveries, returns, price changes, credit holds, cancelled orders.
Use realistic data
Test with migrated data, not demo data. Real products, customers and prices expose problems that demo data hides. This also tests the data migration.
Who tests
Key users from each department, with time freed from their day jobs. A tester who is also covering their full workload will rush.
Log issues properly
For each issue record: scenario, steps, expected result, actual result, screenshot and severity. Use categories:
- Critical: blocks go-live
- High: serious, needs a workaround
- Medium/Low: fix after go-live
Exit criteria
Agree in advance what "done" means, for example:
- All critical scenarios passed
- No open critical issues
- High issues have agreed workarounds
- Reports reconcile with test data
Sign-off
Process owners sign off their areas. This is a commitment that the business is ready, not just IT.
Common mistakes
- Testing only the happy path
- Partner staff testing instead of users
- No time for re-testing fixes
- Skipping integrations and printed documents
After UAT, move on to the ERP go-live checklist. See also common ERP implementation mistakes.
Frequently asked questions
Who should do ERP user acceptance testing?
The people who will use the system: process owners and key users from each department, not the implementation partner.
How long does ERP UAT take?
Typically two to four weeks for a mid-sized project, including fixing issues and re-testing.
Written by
ERP Builders Team · ERP consultants and engineers
Articles written and reviewed by the ERP Builders delivery team — functional consultants, solution architects and developers who implement, integrate and support ERP systems.
Related articles
ERP Implementation Guide: How to Plan, Run and Finish an ERP Project
A practical ERP implementation guide from people who run them: phases, roles, decisions that are hard to reverse, data migration, testing, training and the first month after go-live.
ERP Change Management: Getting People On Board
A practical guide to ERP change management: executive sponsorship, communication, champions, process ownership, training, go-live support and measuring adoption.
ERP Implementation Team: Roles and Responsibilities
Who you need on an ERP implementation team: sponsor, project lead, key users, data owner, consultants and developers, with realistic time commitments.
Next step
Turn the plan into a working system.
Book a consultation with an ERP consultant. No sales script — just an honest look at your situation.